Click below to check out this week’s progress update on our latest build, B43 Fiona K III Week 24 2018. Work is ongoing all over the vessel but this week we are looking at wheelhouse, engine room and forward of the vessel. Work is continuing onboard from KER and Seaquest Systems while our own staff are doing a lot of work in the engine room and elsewhere.

In the engine room, piping for the steering has neared completion while work on the exhaust system is beginning. Also featured in the gallery below is a bilge manifold which is being installed beside the main engine. In accommodation, work is now starting on erecting the walls that will separate out the living quarters, galley etc.